Last September, showing up for Discover Leesburg meant parking somewhere along 5th Street, walking half a block to Towne Square, and catching the last hour of the Evening Market before the vendors packed up. This September, that same stretch of 5th Street has a construction fence running through it. The market is still happening. The parking spot you used last year is gone, at least for now.
That's the story nobody's telling about downtown Leesburg this fall: the calendar is fuller than it's been in years, and it's running directly through the middle of a parking project that hasn't finished adding the spaces it promised.
The corridor doing double duty
The city broke ground this year on the 5th Street Downtown Parking Project, a $1.07 million redevelopment of the former Leesburg Center for the Arts site at 429 W. Magnolia St. The plan is to turn that property and the surrounding area into an expanded public lot, nearly doubling the existing 107-space parking area. The city's own May announcement put the new capacity at 48 additional spaces; by the time officials broke ground in June, the number being cited had grown to roughly 100. Either way, the corridor is getting more parking than it has now. It just isn't finished getting it.
Work is unfolding in three phases. Phase 1, initial infrastructure and site clearing, began in May 2026. Phase 2, the expanded site and streetscape work, began in August, which is where things stand today. Phase 3, the final corridor enhancements, doesn't start until November, with completion expected by the end of that month.
Here's the detail that matters if you live near downtown: the same 5th Street corridor under construction is the corridor the city uses every second Friday for Discover Leesburg's Evening Market. The event isn't happening despite the construction. It's happening on top of it.
What's actually on the calendar before the ribbon gets cut
This isn't a quiet season to skip downtown until the dust settles. Between now and the holidays, Leesburg's Towne Square and Main Street are hosting:
- Discover Leesburg, the second-Friday live music and Evening Market series, continuing on September 11 from 5 to 9 p.m., with the market itself set up on 5th Street
- Fiesta en la Plaza, the city's Hispanic Heritage Month celebration, on September 25 from 6 to 10 p.m. at Towne Square
- A Haunted House inside the Mote-Morris House, October 29 through 31 from 7:30 to 10 p.m., five dollars a person, a rare after-dark opening of one of downtown's oldest landmarks
- Trick or Treat on Main Street, October 31 from 4 to 7 p.m., with downtown businesses handing out candy along the sidewalk
- The Veterans Day Parade, marching down Main Street on November 11
- The Flapjack 5K, a pancake-themed run and brunch festival at Towne Square on November 14
- The Christmas Festival & Parade, back at Towne Square on December 12
Five of those seven land squarely inside the Phase 2 and Phase 3 construction window. Only the December events have a real shot at overlapping with a finished lot, and even that depends on the project wrapping on schedule.
Worth separating out: Light Up Venetian Gardens and its boat parade, set for December 6, isn't part of this at all. That event happens at Venetian Gardens and Ski Beach, a different stretch of the lakefront entirely, well outside the 5th Street construction zone. If your plans this winter are boats and lights rather than Main Street and Towne Square, the parking project simply doesn't touch you.
The businesses feel it first
Downtown's restaurant row sits right along the corridor in question. Turners, the New American spot on South 5th Street, and Vanderbrew on West Main Street are both a short walk from the construction site. So is Great Chicago Fire, the brewpub, hot dog, and pizza bar a block over, whose owner was asked by a local reporter whether the project would hurt foot traffic and gave a simple answer: no.
That's consistent with how the city has framed the project from the start. One local Chamber of Commerce board member, describing the plan after the groundbreaking, put the upside plainly: the roughly 100 new spaces are meant to "improve traffic flow and connectivity, enhance lighting and landscaping" and support downtown's continued growth. Nobody's arguing the project is bad for Leesburg. The disagreement, if there is one, is about timing. A parking lot that finishes in late November helps the Christmas Festival. It doesn't help Fiesta en la Plaza in September, and it's still mid-build for the Veterans Day Parade in November.
A resident's plan for the next three months
None of this means downtown is off-limits. It means the habits that worked last fall need a small update.
The Magnolia Street lot being expanded is itself the construction site, so it's not a safe assumption as overflow parking right now, and 5th Street is the segment doing the heaviest work between now and November. For anything with a hard start time, like the Flapjack 5K's race clock or the Veterans Day Parade's route closures, arriving twenty or thirty minutes earlier than you would have last year is the simplest fix. Walking or biking in from the surrounding neighborhoods, always an option in a downtown this compact, matters more this season than it has in past years.
For Fiesta en la Plaza specifically, now in its second year and clearly growing in scale, the crowd itself is likely to be bigger than last September's turnout even before construction is factored in. That combination, more people and fewer curbside spaces, is the one worth planning around most.
What this means if you already call Leesburg home
The short version: downtown isn't shrinking, it's mid-renovation, and the fall calendar didn't wait for the construction schedule to clear before filling back up. That's a good problem for a small city to have. It's also the kind of detail that only shows up if you're paying attention to both the events page and the public works updates at the same time, which most people planning a Friday night out understandably aren't.
That's the same lens we bring to the neighborhoods we work in every day, watching the small civic details that shape daily life here, not just the listings. If you're weighing a move within Lake County, thinking about what a property near downtown Leesburg is actually like to live with day to day, or just curious what else is changing across western Orange and Lake County this season, Autumn Makin would be glad to walk you through it. Schedule your free home consultation and valuation whenever you're ready to talk specifics.